After the installation and debugging of the machine tool is completed, the manufacturer will be notified to send someone to debug the machine tool. The tests mainly include the following:
1. Various manual tests
a. Manual operation test: Test the accuracy of manual operation.
b. Inching test
c. Spindle gear shifting test
d. Overtravel test
2. Functional test
a. Use buttons, switches, and manual controls to conduct functional tests on the machine tool. Test the flexibility, smoothness of the action and the reliability of the function.
b. Select any spindle speed to conduct continuous tests of spindle start, forward rotation, reverse rotation, and stop. Operate no less than 7 times.
c. Spindle high, medium and low speed conversion test. The allowable difference between the command value of the speed and the displayed value is ±5%.
d. Select any feed amount, and continuously perform working feed and rapid feed tests on the entire XZ axis travel. The rapid stroke should be greater than 1/2 full stroke. No less than 7 positive and negative squares and consecutive operations.
e. Conduct low, medium and high feed conversion tests on the entire travel of the X and Z axes. The turret tool holder undergoes various indexing clamping tests.
f. The hydraulic, lubrication, and cooling systems are tested for sealing, lubrication, and cooling to ensure there is no leakage.
g. The chuck is tested for clamping, loosening, flexibility and reliability.
h. The spindle is tested for forward rotation, reverse rotation, stop and change of spindle speed.
i. The turret tool holder undergoes a forward and reverse direction indexing test.
j. The feed mechanism performs a rapid feed conversion test with low, medium and high feed amounts.
k. Test feed coordinate overtravel, manual data input, position display, return to reference point, program number instruction and retrieval, program pause, program deletion, address line interpolation, straight line cutting hesitation, taper cutting cycle, thread cutting cycle, circle The reliability and movement flexibility of arc cutting cycle, tool position compensation, pitch compensation, gap compensation and other functions.
3. Idling test
a. The operation test of the active driving mechanism shall not be less than 1 hour at the highest speed range, the temperature of the main shaft bearing shall not exceed 70°C, and the temperature rise shall not exceed 40°C;
b. Continuous dry running test, the running time is not less than 8 hours, and each cycle time is not more than 15 minutes. The machine stops at the end of each cycle and simulates the action of loosening the workpiece. The machine stops for no more than one minute and then continues operation.
4. Load test
Users prepare drawings and blanks of typical parts, program and input the program under the guidance of the manufacturer's debugging personnel, and select cutting tools and cutting quantities. The load test can be carried out in the following three steps: rough turning, heavy cutting, and fine turning. Each step is divided into single cutting and cycle program cutting. After each cutting is completed, the actual size of the machined part of the part is inspected and compared with the command value. The operating accuracy of the machine tool under load conditions is inspected, that is, the overall machining accuracy of the machine tool and the indexing accuracy of the turret tool holder.
5. Acceptance
After the machine tool is unpacked and accepted, the functional test, dry running test, and load test are completed, and qualified products are processed, the acceptance and handover procedures can be completed. If there are any problems, the manufacturer should be responsible for solving them.
CNC lathe start-up test